MAXSPAN

Best Quality & Priced Post Driven Fixed Tilt Systems

CLICK TO REQUEST A QUOTE

MaxSpan Post Driven System - with Aluminum Framed Modules

  • Complete install rate including moving materials from staging area: .565 worker hours per module equivalent
  • Complete install rate with 20 workers per week: 5.38 MW
  • Module-only install rate: 464 modules per worker per day

Time Study

MaxSpan Post Driven System - with Aluminum Framed Modules

WideFlange

  • Industry’s most flexible racking system handles undulating ground conditions
  • Telescoping post bracket with up to 5"[12.7 cm] vertical adjustment for fast top of post leveling

WideFlange

Optimal System for Undulating Ground Conditions

Superior Terrain Navigation Adjustability

Articulating purlins between tables enable installation on sites with complex slope issues, which when combined with post and post bracket adjustment handle up to 15% east‑west terrain slopes and undulations

Articulating purlin connections combine with slots or post brackets to navigate up to 15% terrain slopes

Purlins for all MaxSpan™ systems have multiple mounting holes allowing 6"[15.24 cm] east‑west adjustability


MaxSpan FastBuild

Industry’s Lowest Part Count of all Post Systems


  • Industry’s fastest install system due to minimal parts
  • Lowest A frame part count of any system, just 3 parts (post, beam and brace) and 6 bolts for 2 up
  • StickyPost™: G235 [55 μm] galvanized steel (HDG available), purlins, beams & braces: G90 [20 μm] galvanized steel
  • Three axes of adjustability demanded by installers for navigating real world site conditions where significant adjustability in the field is required
  • The unmatched span capability of the MaxSpan™ means there are fewer foundations than competing systems, which also means less posts and less post installation cost. As few as 190 posts per MW
  • Standard system has 6” + 3.5” [15 + 9 cm] vertical adjustability
  • Optional post extenders allow 10" [25.4 cm] vertical adjustability

Typical Part Count Comparison vs. Competitors for A Frames (Post, Brace, Beam and Related Brackets)

Components Bolts Total Parts Posts/MW Total Components Per MW
MaxSpan™ 3 6 9 215 645
Competitor A 5 8 13 250 1254
Competitor B 5 14 19 250 1254
Competitor C 8 14 22 250 2008

Nesting components eliminate brackets, have long slots enabling 3 axes of adjustability.

GameChange StickyPost

Long slots allow 3.5"[8.89 cm]
vertical adjustability

Optional post extenders allow 10"[25.4 cm] vertical adjustability

Features

  • Supports all double-sided glass thin film & other modules
  • Up to 4 ft.[121.92 cm] ground clearance eliminates snow & vegetation shading issues
  • Galvanized Z purlins have integrated trays for easy wire management
  • 5 to 35° tilt with multiple inter-row spacing options
  • Stamped layout & engineering analysis for every project
  • Integrated grounding with star washers or teethed module clamps included - approved under ETL /UL 2703

Features

Self Hanging Purlin

  • Reduce labor for purlin mounting by 40% because two men can place purlins on supports and then one man can bolt them on versus five man team previously
  • Available Q4 2017

Self Hanging Purlin

3-Up Portrait Option Available

  • Typically 5% or more lower system cost
  • Wider row spacing
  • Reduces number of foundations per MW up to 30%

3-Up Portrait Option Available

First Solar Series 4 Mounting Solutions

  • The GameChange MaxSpan offers a mounting solution for the high performing and efficient First Solar Series 4 module. Three First Solar Series 4 modules are held on top of each pair of purlins in landscape configuration.
  • The GameChange MaxSpan First Solar module configuration helps improve energy production by increasing the module density on each table.

First Solar Series 4 Mounting Solutions

Solar Frontier Mounting Rails

  • The GameChange MaxSpan offers a mounting solution for the high performing and efficient Solar Frontier CIS module. Two Solar Frontier CIS modules are held in between each pair of purlins in portrait configuration.
  • The GameChange MaxSpan CIS module configuration helps improve energy production by increasing the module density compared to the competition.

Solar Frontier Mounting Rails

Helical Post System - Single Post

  • Optimal for peat bogs and other very soft soils or areas with frost jacking concerns
  • Dual post also available

Helical Post System - Single Post

Superior Bankability

At GameChange Solar we're changing the world by making solar energy affordable

gamechange solar
.+
GIGAWATTS OF GAMECHANGE SOLAR SYSTEMS
gamechange solar
. million+
SOLAR MODULES ON GAMECHANGE SOLAR SYSTEMS
gamechange solar
. million+
CO2 TONS OFFSET OVER 25YRS BY MODULES ON GAMECHANGE SYSTEMS
gamechange solar
. billion+
OIL GALLONS OFFSET OVER 25YRS BY MODULES ON GAMECHANGE SYSTEMS